Upcoming Construction Activities Crews will continue trenching for fiber conduit installation in the traffic lanes at the following locations: - Milepost (MP) 470.5 to 472.5 (near Right Hand Fork)
- Milepost 486 to 487 (near SR-243)
This work includes rock saw excavation, allowing for precise material removal with minimal impact to surrounding structures.
Additionally, crews will perform milling on Monday, June 16, followed by paving operations on Tuesday and Wednesday, June 17–18, between MP 487 to 488. Please drive with caution through the work zones.
Drivers can anticipate traffic delays and signalized one-way traffic at multiple locations throughout the project area. |