UDOT Update for Fiber and Repaving Near Beaver Creek

 

Construction Update | July 11, 2025

Upcoming Construction Activities

Crews will continue trenching for fiber conduit installation in the traffic lanes at the following locations:

  • Milepost (MP) 475.5 to 477.5 (near Temple Fork Rd)
  • Milepost (MP) 482.5 to 484.5 (near Franklin Basin Rd)


This work includes rock saw excavation, allowing for precise material removal with minimal impact to surrounding structures. Please drive with caution through the work zones.


Drivers can anticipate heavy traffic delays and signalized one-way traffic at multiple locations throughout the project area.

Driver Safety Reminders: Use caution and prioritize safety while travelling through the construction area. Reduce speed, follow posted signage and be alert of crew members and equipment.

Crews installing fiber optic conduit along US-89 in Logan Canyon.

Beaver Creek Project: The Utah Department of Transportation (UDOT) is completing a roadway replacement project on US-89 from Beaver Creek Resort to milepost (MP) 492 in Logan Canyon, spanning approximately 6 miles. Work is anticipated to begin on Wednesday, July 16. Drivers can expect heavy delays. For additional adjacent project information, visit our website.

Project Overview

UDOT is installing fiber optics cable in Logan Canyon. This fiber optic cable installation will improve broadband access in Logan Canyon, allowing for easier and more reliable community connection for Logan City, Garden City, and Beaver Mountain Resort. It will also strengthen and enhance communication capabilities, strengthen emergency service support, and create opportunities for these communities to expand services and improve connectivity. To Learn More, view the Project Video.


Work began in early May and will be completed in fall 2026.*

What to Expect

  • Monday - Thursday 7 a.m. - 5 p.m. / Friday 7 a.m. - 12 p.m.
  • Occasional weekend and night work
  • Winter shutdown with finish work through fall 2026
  • Moving operations throughout the canyon
  • One way traffic with temporary signals, at various locations
  • Delays are anticipated throughout the canyon
  • Nighttime lighting, noise, dust, and vibration
  • Heavy equipment, support vehicles, and crew members

CAUTION: Motorcyclists and cyclists

  • Uneven roadway surface in travel lanes


*Construction schedules and traffic impacts are subject to change

due to weather, utility, equipment, and material delays.

Project Map

Stay Informed

Want the latest? Sign up for email updates by emailing logancanyonfiber@utah.gov with "Subscribe" in the subject line.

Know before you go!

Check UDOT Traffic today!


The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways.


Download for Android

Download for Apple

Contact Us

Public Involvement Team

Hotline: 801-996-7086

Email: logancanyonfiber@utah.gov

Website: udotinput.utah.gov/logancanyonfiber

Public Involvement Team | 111 E Broadway Suite 600 | Salt Lake City, UT 84111 US