Anita Weston, Reporter
Rich Civic Times
GARDEN CITY, Utah. September
12, 2013. Riley Argyle, supervisor of the Public Works Department reported to
the City Council his activities during the past month. In preparing the master water plan, JUB
Engineering collected data for the City in July and ran some flow tests and
pulled data logs from the big meters for JUB at that time. They requested some additional data which
takes July 24 and up to the present time.
This should give them enough data to put together a plan by the end of
October.
The City has been mowing all
of the reeds and vegetation along the beach contained within the City limits. Also signs of “Walk Only” for beach access was
installed on 150 South, 200 North, and 75 North. There are more signs that need to be placed
as soon as the locations are identified.
More “No Parking” signs have been ordered and the big rocks at 250 East
have been moved and the gates were removed.
The gun range will be a
partnership with the state (their land) the county (building road in and
parking area) and Garden City (obtain equipment, bathrooms, water, and run the
facility). This project is still in the
conceptual phase. Danny White (the City
Administrator) has drawn up the master plan and is working with the Sweetwater
HOA. There are funds available for such
a project from the DNR. This proposed
project may qualify for some of these funds.
It was noted that grant requests need to be written up to apply for
these monies.
A formal proposal for the gun
range needs to be drawn up. The
partnerships need to be formalized and documentation of the deer and sage
grouse usage study will need to be provided.
Also, additional adjacent landowner input needs to be obtained.
The kiosk is still in the
building phase. Materials have been
difficult to obtain and get to the site which has slowed down this project
tremendously. Hopefully, it will be completed
in the near future.
The Bear Lake Water Company
has an abandoned well. The City decided
to investigate to see if it would be possible to use that well to take care of
some of the City’s water demands.
Glenn’s Electric came and used a camera to check out the well. It was discovered that the well is 340 feet
deep and needs to be cleaned. The well
appears to have good potential. Bear
Lake Water Company will turn the well over to the City for 15 shares of water
currently owned by the City in Hodges Irrigation Company. The City is currently working on getting a
permit for renovating the well. Also
MOUs need to be written and signed to make sure everyone understands the
arrangements that have been agreed upon.
The cost of cleaning and
testing the amount of water available by pumping will cost about $50,000. The water shares used in the exchange have
been valued at $3,000 each, costing $45,000.
Digging to get the needed pipes in place and power to the site are
additional costs estimated at approximately $20,000. This will also include source protection plan
along with a well protection plan.
The City continues to GPS as
many of the meters and valves currently in the water system. It is going well but will take additional
time before this project is complete.
The City’s light project is
moving along well. Fifteen of the 20
lights have been installed. Four of the
remaining lights have been requested leaving one left to put in place.
The main water line into
Lakota is being replaced so that the pipes won’t freeze in the winter. The road there is only 15 feet wide which
doesn’t allow much room to lay pipe and still have people drive along that
area. This project involves 11
meters. It should be completed in the
next week or two.
The parking lot on 75 North
is complete. There needs to be more red
paint on the corners to let people know to now park quite so close to the
highway. The trees are doing well. Currently they are being watered two or three
times a week. Soon, the City will be
able to cut back on that as the trees become acclimatized. Placement of a
couple of dumpsters needs to be determined.
There are two Idaho water users who
are still on hold. The meter project is
complete for five of the users.
There have been some problems
at the water treatment plant. The
chlorine pump is leaking. The sodium
hypochlorite machine needs an acid wash every month. The City has purchased the necessary tools
and the workers are now taking care of this item. It saves $1,000 a month. The piping for the hypochlorite was plugged
off and needed replacement. It was
determined that a different plumbing arrangement would actually cut down on the
amount of particles that are currently filling up the hypochlorite pipes. It has taken about a week to make all the
needed changes and modifications.
Hopefully, these changes will allow for better use down the road. Two trees at the water treatment plant need
to be replaced. The landscaping has been
finished.
Water’s Edge Subdivision went
before Planning and Zoning last week.
The Committee denied the conceptual plan because there are several
studies that need to be completed prior to approval being granted.
Pickleville Commons has been
red flagged. There are some water issues
that must be taken care of by the state before additional work can be done at
that subdivision. Because the City does
not have a full-time engineer, the State has to take over that responsibility
to check all water projects undertaken.
This is the case in this situation.
The State needs to make sure all water items are meeting state
requirements.
Originally, the trailhead at Hodges Canyon
was a partnership between the City and State.
The State was responsible to keep the bathroom clean, and the City was
to maintain the parking lot. The State
has not been taking care of the bathrooms.
Contact has been made with the State and hopefully this matter will soon
be resolved.
Argyle has been invited to
join a North Utah Water Alliance. The
individuals who belong to the organization all work with water treatment
plants. The members are kept aware of
any law changes and form networking connections when problems or questions
arise. The Council encouraged him to
join this organization.
The City’s backhoe lease is
up. The cost this year will be a bit
cheaper than last year. We will still be
getting the John Deere brand of backhoe.
The trailer house on 75 North
on the north side of the road in the middle of the block is a hazard. It needs to be condemned. George Peart, the Building Inspector, was
asked to check into this matter and see about the trailer’s removal.
There have been 26 building
permits issued so far this year in Garden City. Peart noted that Laketown currently has 6
building permits.
Peart was informed that a
garage on the Hillier property was built over the Labor Day Weekend. No permit had been issued. He was asked to check into this matter. The Council also informed that all water
issues on homes must have engineering approval.
Since the City does not have a full time engineer, this responsibility
falls to the state. Thus, the state must
be informed and given an opportunity to inspect each project undertaken dealing
with water.
No comments:
Post a Comment