Anita Weston, Reporter
Rich Civic Times
GARDEN CITY, Utah. December 14, 2017. Riley
Argyle, Supervisor of the Public Works Department, noted that the Garden City
Fire Department is going to add onto the current building this coming
spring. There are four trees on the west
side of the building that are going to have to be taken down. Riley suggested that the City get the four
trees and plant them at Heritage Park.
It would cost of City about $3,500 to dig the trees and move them to the park, they are about 15’-20’
high and would add to the park. The City
is going to have to get even more trees for the park, and the moving expense
are all that these four will cost the City.
The
water treatment plant has a problem with the flow switch. It keeps blowing out. Argyle contacted IFM in New Jersey for help
with the problem and got a new switch.
There were still issues three days after it was installed, and it also
blew up. Argyle found the individual who
put the flow switch in originally. His
name is Patrick Hayes, and he lives in Boise. Argyle has called and left message with him hoping that he will be able
to help out. Argyle suggested that in the
future, items purchased need to have local service available so that when
problems like this occur, help can be obtained.
There
was another problem at the Water Treatment Plant. There is an automatic arm that moves across a
screen to clear it. The arm slipped and
went too far. Argyle ordered the parts
that limits the switch brake so that the arm doesn’t go beyond the area it
covers. He was able to put
the
parts in place so that it is now working properly. The parts cost $4,500.
The
Public Works Department has been working on the dump truck that has a snow plow
mounted on the front. They are trying to
fix it so that the sand won’t shift when they are plowing snow.
Argyle reported that Chuck Stocking was able to pull all of the GIS information from
the old computer to a new one after the old one died. Everyone thought the information would be
lost when that computer went down which would have caused hours of work redoing
all required GIS information. Argyle is
always adding new GIS information so that updating is happening all of the
time. He will print the information and
put it in a book and make sure the information is on file in case something
happens to the new computer.
Some
employees have been working on the lake access south of Legacy. That access is about 75 percent
complete. These employees have been
pulled off the project because it gets dark so early. The City will try and hire someone to
complete this project. A bid needs to be
put out to hire someone to finish up the fencing and retaining wall on this
access. Three individuals had been
hired, but they didn’t get the work done.
It needs to be finished.
All
of the accesses that go to the lake that have been turned back to the
subdivision need to be recorded. The MOU
that was made put this responsibility onto the City. But so far, the City hasn’t taken care of
this matter. It should be done soon.
An
air compressor at one of the water pumping areas quit. The parts needed were ordered and have
arrived. Argyle will get it fixed as soon
as possible.
The
pellet stove at the water treatment plant needed to be replaced. A new one was purchased and installed. It is running well now.
The
heater in the building at the bottom of Elk’s Ridge broke. It will need to be replaced. There are some options on this item. There are a lot of high tech items that have been built into these types of heaters that make them very efficient. This is the direction the City should go as
they purchased the new heater.
The
parking area at Heritage Park is fixed.
There was a moisture problem that has been resolved.
No comments:
Post a Comment