Traffic Signal Installation
This week, concrete pouring will start on the East side of the project while crews prepare the West side of the intersection. After the East side has been completed, the West side concrete will be poured. Throughout construction, crews will maintain pedestrian access as much as possible in the area.
Crews may begin paving asphalt as early as the week of June 15th and paving operations will also move from the East side of the intersection to the West side.
This project will install a new traffic light signal at the intersection of U.S. 89 and Bear Lake Boulevard, improve pedestrian facilities, and formalize the driveway into Raspberry Square. The project is anticipated to be completed by mid-summer.
No comments:
Post a Comment