Construction Update July 24, 2025

 

Construction Update | July 24, 2025

Rick Springs Fire

Due to the Rick Springs Fire, crews may work until late evening. Drivers should expect uneven surfaces, and additional delays.

Raspberry Days

Construction activities will pause from Wednesday, August 6 at 12 p.m. through Monday, August 11 at 7 a.m. Security and construction barrels will remain in place to protect the work zones.

Upcoming Construction Activities

Crews will continue trenching for fiber conduit installation in the traffic lanes at the following locations:

  • Milepost (MP) 470 to 472.5 (near Right Hand Fork)
  • Milepost (MP) 481 to 484 (near Tony Grove Rd)


This work includes rock saw excavation, allowing for precise material removal with minimal impact to surrounding structures. Please drive with caution through the work zones.


Drivers can anticipate heavy traffic delays and signalized one-way traffic at multiple locations throughout the project area.

Beaver Creek Project: The Utah Department of Transportation (UDOT) is completing a roadway replacement project on US-89 from Beaver Creek Resort to milepost (MP) 492 in Logan Canyon, spanning approximately 6 miles. Work began on Wednesday, July 16. Drivers can expect heavy delays. Logan Canyon Closure: US-89 will be fully closed between MP 485 and 491 beginning July 28 and 29, from 10:00 p.m. to 6:00 a.m. each night. A detour will be in place utilizing US-39. Please plan ahead and follow posted signage. For additional adjacent project information, visit our website.

CAUTION: Motorcycle, Cyclists, and Drivers

There are trenches, uneven road surfaces, and loose gravel throughout the corridor. Please use caution and prioritize safety while travelling through the construction area. Reduce speed, follow posted signage, and be alert of crew members and equipment.

Crews installing fiber optic conduit along US-89 in Logan Canyon.

Project Overview

UDOT is installing fiber optic cable in Logan Canyon. This fiber optic cable installation will improve broadband access in Logan Canyon, allowing for easier and more reliable community connection for Logan City, Garden City, and Beaver Mountain Resort. It will also strengthen and enhance communication capabilities, strengthen emergency service support, and create opportunities for these communities to expand services and improve connectivity. To Learn More, view the Project Video.


Work began in early May and will be completed in fall 2026.*

What to Expect

  • Monday - Thursday 7 a.m. - 5 p.m. / Friday 7 a.m. - 12 p.m.
  • Occasional weekend and night work
  • Winter shutdown with finish work through fall 2026
  • Moving operations throughout the canyon
  • One way traffic with temporary signals, at various locations
  • Delays are anticipated throughout the canyon
  • Nighttime lighting, noise, dust, and vibration
  • Heavy equipment, support vehicles, and crew members
  • Utah Highway Patrol escorts in the area



*Construction schedules and traffic impacts are subject to change

due to weather, utility, equipment, and material delays.

Project Map

Stay Informed

Want the latest? Sign up for email updates by emailing logancanyonfiber@utah.gov with "Subscribe" in the subject line.

Know before you go!

Check UDOT Traffic today!


The UDOT Traffic app provides commuters and travelers with mobile access to information for the State of Utah roadways.


Download for Android

Download for Apple

Contact Us

Public Involvement Team

Hotline: 801-996-7086

Email: logancanyonfiber@utah.gov

Website: udotinput.utah.gov/logancanyonfiber

No comments: