Logan Canyon Fiber Project Update

 

Construction Update | August 21, 2025

Labor Day Holiday

Construction activities in the canyon will pause on Friday, Aug. 29 at 12 p.m. through Tuesday, Sept. 2 at 7 a.m. Lanes are fully restored and traffic impacts are not anticipated during this time. Security and construction barrels will remain in place to protect the work zones.

Upcoming Construction Activities

Crews will continue trenching for fiber conduit installation in the traffic lanes at the following locations:

  • Milepost (MP) 462.5 to 463.5 (near Canyon Rd and Canyon Entrance Park)
  • MP 474.5 to 476.5 (near Right Hand Fork)


Crews will continue paving in the traffic lanes at the following locations:

  • MP 474 to 478 (near Temple Fork Rd)


This work includes rock saw excavation, allowing for precise material removal with minimal impact to surrounding structures. Please drive with caution through the work zones. Impact to travel will be minimal near Canyon Entrance Park, but traffic will occasionally have to stop for 5 minutes for machinery maintenance.


Drivers can anticipate heavy traffic delays and signalized one-way traffic at one location throughout the project area.

So why Fiber Optics?

While we often discuss the benefits of high-speed fiber internet, it’s equally important to understand the technology that makes it all possible.

  • Carries Telephone Calls: Fiber optics are not just for internet; they also carry telephone calls using a technology known as Voice over Internet Protocol (VoIP).
  • Data in Light Form: Fiber optics transmit data in the form of light signals, and the light reflects internally as it travels down the cable.
  • Energy Efficiency: Fiber optic technology is energy-efficient as it requires less power for signal transmission.

Fiber Optic Cables along US-89

CAUTION: Motorcycle, Cyclists, and Drivers

There are trenches, uneven road surfaces, and loose gravel throughout the corridor. Please use caution and prioritize safety while travelling through the construction area. Reduce speed, follow posted signage, and be alert of crew members and equipment.

What to Expect

  • Monday - Thursday 7 a.m. - 5 p.m. / Friday 7 a.m. - 12 p.m.
  • Occasional weekend and night work
  • Winter shutdown with finish work through fall 2026
  • Moving operations throughout the canyon
  • One way traffic with temporary signals, at various locations
  • Delays are anticipated throughout the canyon
  • Nighttime lighting, noise, dust, and vibration
  • Heavy equipment, support vehicles, and crew members
  • Utah Highway Patrol escorts in the area



*Construction schedules and traffic impacts are subject to change

due to weather, utility, equipment, and material delays.

Project Overview

UDOT is installing fiber optic cable in Logan Canyon. This fiber optic cable installation will improve broadband access in Logan Canyon, allowing for easier and more reliable community connection for Logan City, Garden City, and Beaver Mountain Resort. It will also strengthen and enhance communication capabilities, strengthen emergency service support, and create opportunities for these communities to expand services and improve connectivity. To learn more, view the Project Video.


Work began in early May and will be completed in fall 2026.*