GARDEN CITY, Utah. January 9, 2014. The Garden City Town Council held their
regularly scheduled meeting and heard an
update from Riley Argyle, Public Works Department which included the following:
Water master plan
. On July 9th JUB ran some
flow test
.
Pulled data logs from big meters for JUB
. Working with Lewis and Young
Engineering on impact fees and rates
Garden City Gun Range
. Project
in conceptual phase
. Can
receive only one hundred thousand in funding from state
. Signed
an M.O.U. with the county
. Danny
White has completed the master plan
Heritage Park
. The well is done and is on a monitoring
device that shuts off when the water drops
. Waiting on plans to install infrastructure,
sprinklers, power, and seed
Heritage Park Pond
. Have dock for ADA at the fish pond
Light Project
. Four lights are left to be installed
300 West (South) Water
Line/Ditch Work
. Started the ditch work, and have most of the
pipes for project
. The
project needs a 14” line installed for bypass reasons and to serve properties
along with water and fire flow. The line
will need to be installed from 300 W/US 89 to Buttercup. Public Works will try to do some of the labor
themselves, but the materials will be a major project.
Idaho Water Meters/Line
. Two meters are left
GIS Mapping
. The new unit is working and have
collected GIS points, and have all the valves for the south end of town up to
300 West
.
Put 100 new points on the map
.
Most of the water meters on the south end of town are done
Garden City Park
. Add more parking to the south and east of park
. Build
a new well to run the sprinklers
. Help
Lance Bourne move his shed down by the beach bathrooms
Shundahai Subdivision
.
Pump house was flooded due to vandalism, this issue is being resolved
.
Easements, right of ways, or deed shave not been received. (Overdue as
of December 31, 2013)
. Dam
on their storm water collection pond as been cut
. Power is not installed correctly