Anita Weston, Reporter
Rich Civic Times
GARDEN CITY, Utah.
September 11, 2014. Water meters
need to be installed in the Birth Subdivision.
There are at least seven homes that have never been metered. There are still approximately 35 homes in the
City that haven’t had water meters put in place. Progress is being made, but it is a difficult
challenge. Where the homes connect to
the water is a real problem. Most of the
pipes that have been used are plastic and can’t be located using metal
detectors. There has been and will be a
lot of digging done in order to find the lines and connection points.
The City is currently working with Lewis and Young on water
impact fees and rates. The impact fees
need to be reworked to take into consideration the pay back for the use of the
Shundahi tank.
The main head gate on the Logan road is now in place. Water will be piped from this location down
and under 300 West. The City has
purchased 350 feet of pipe and 5 to 10 head gates that need to be
installed. A few more head gates will be
needed. There will be approximately 7 or
8 laterals that will need to be placed along 300 West. This project will probably be put out to bid.
The City has a few chlorine leaks so that replacement of
some of the lines will need to be taken care of this fall.