RANDOLPH, Utah. October 3, 2018. Engineers from Jones and DeMille Engineering
reported that Cisco Road is paved to south Eden and two thirds of the project is
seeded. Signs and delineators are being
installed. The rest should be paved
during November, and a center lane will be striped.
They are getting 92% compaction of the asphalt, so they are
under the budget by $100,000. They need to build a retaining wall at the
Scout Camp for the bike trail. Rocky
Mountain Power ran underground power lines south of the Scout Camp for one half
mile. There are also new poles and power
along the rest of the road. Centra Com
has buried conduit for future use.
They are right on schedule within two or three days. Next year they will chip and seal and then
mark it more thoroughly. They had 20 trucks of asphalt a day average coming to
the site. Whitaker construction is the contractor.
Commissioners praised the
work and suggested that they need to stripe the bike lane right away so
heavy trucks don’t get on the bike path.