Logan Canyon Fiber Update
Construction Update | August 1, 2025 |
|
Raspberry Days Construction activities in the canyon will pause on Wednesday, August 6, at 12 p.m., through Monday, August 11 at 7 a.m. Work in Logan City near the entrance of canyon will pause on Wednesday, August 6, at 5 p.m., through Monday, August 11 at 7 a.m. Security and construction barrels will remain in place to protect the work zones. |
|
Upcoming Construction Activities Crews will continue trenching for fiber conduit installation in the traffic lanes at the following locations: - Milepost (MP) 460 to 461.7 (near Canyon Rd and Canyon Entrance Park)
- MP 480.5 to 482.5 (near Tony Grove Rd)
This work includes rock saw excavation, allowing for precise material removal with minimal impact to surrounding structures. Please drive with caution through the work zones. Impact to travel will be minimal near Canyon Entrance Park, but traffic will occasionally have to stop for 5 minutes for machinery maintenance.
Drivers can anticipate heavy traffic delays and signalized one-way traffic at one location throughout the project area. |
|
CAUTION: Motorcycle, Cyclists, and Drivers There are trenches, uneven road surfaces, and loose gravel throughout the corridor. Please use caution and prioritize safety while travelling through the construction area. Reduce speed, follow posted signage, and be alert of crew members and equipment. |
|
Crews installing fiber optic conduit along US-89 in Logan Canyon. |
|
Project Overview UDOT is installing fiber optic cable in Logan Canyon. This fiber optic cable installation will improve broadband access in Logan Canyon, allowing for easier and more reliable community connection for Logan City, Garden City, and Beaver Mountain Resort. It will also strengthen and enhance communication capabilities, strengthen emergency service support, and create opportunities for these communities to expand services and improve connectivity. To Learn More, view the Project Video.
Work began in early May and will be completed in fall 2026.* |
|
What to Expect- Monday - Thursday 7 a.m. - 5 p.m. / Friday 7 a.m. - 12 p.m.
- Occasional weekend and night work
- Winter shutdown with finish work through fall 2026
- Moving operations throughout the canyon
- One way traffic with temporary signals, at various locations
- Delays are anticipated throughout the canyon
- Nighttime lighting, noise, dust, and vibration
- Heavy equipment, support vehicles, and crew members
- Utah Highway Patrol escorts in the area
*Construction schedules and traffic impacts are subject to change due to weather, utility, equipment, and material delays. |
|
|